https://n am 2 (Chapters 2 to 4) 6 Dagostino Corporation uses a job-order costin
ID: 342445 • Letter: H
Question
https://n am 2 (Chapters 2 to 4) 6 Dagostino Corporation uses a job-order costing system. The following data relate to the just completed month's operations 10 (1 Direct materials requisitioned for use in production,$154,000 (2) Indirect materials requisitioned for use in production $45,000 (3) Direct labor wages incurred $94,000 (4) Indirect labor wages incurred,$119,000 (5) Depreciation recorded on factory equipment $44,000 (6) Additional manufacturing overhead costs incurred $83,000 (7) Manufacturing over (8) Cost of jobs completed and transferred from Work in costs applied to jobs,$236,000 Process to Finished Goods.$458.000 Use the f T-accounts to answer the following questions Bal. $48,000Explanation / Answer
Work in process T Account :
Manufacturing overhead applied :
so answer is c) $74000
Bal. 48000 Direct material 154000 Cost of goods manufactured 458000 Direct labour 94000 Overhead applied 236000 Bal. 74000Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.