Procurement Management w WELY 19. Which of the followving is an adrantage of cen
ID: 343953 • Letter: P
Question
Procurement Management w WELY 19. Which of the followving is an adrantage of centralied contracting A. Increased expertise B. Fasier access C. No home for the peocurement manager D. More loyalty to the project 20. With which type of contract is the seller MOST concermed about project scope A. Fixed price R. Cost plus fxed fee C. Time and material D. Purchase order 21. Your company has an emergency and needs contracted work done as soon as possible. Under these circumstances, which of the following would be the MOST helpful to add to the contract A. A cdlear peocurement statement of work Requirements as to which subcontractiors cam be used C Incentives D. A force majeure clause 2 During which procurememt processes does procurement negotiation occur? A. Plan Procurement Management and Close Procurements B. Control Procurements and Close Procunements C. Conduct Procurements and Control Procurements D. Conduct Procurements and Close Procurements 23. The project team is arguing about the prospective sellers who have submited proposals. One team member argues for a certain seller whille anocher team member wants the project awarded to a different seller. What part of the procurement peocess is the team in? B. Control Procurements C Negotiate Contracts D. Conduct Procurements 24. A project manager is in the middle of creating a request for peoposal (RFP). What part of the procurement process is he in A. Conduct Procurements B. Plan Procurement Management C. Administer Procurements D. Make-or-Buy Analysis 518Explanation / Answer
19. Which of the following is an advantage of centralized contracting
B. Easier Access
20. with which type of contract the seller most concerned about project scope
C. Time and Material
21. Your company has an emergency and needs contracted work done as soon as possible. Under these circumstances, which of the following would be the mist helpful to add to the contract.
C. Incentives
22. During which proicurment process does procurement negotiation occur
A. Plan Procurement Management and Close Procurements
23. The project team is arguing about the prospective sellers who have submitted proposals. One team member argues for a certain seller while another team member wants the project awarded to a different seller. What part of the procurement process is the team in
D. Conduct Procurements.
24. A project manager is in the middle of creating a request for proposal (RFP). What part of the procurement process is he in
B. Plan procurement management