If during a schedule update, the critical path changed, this can be attributed t
ID: 344515 • Letter: I
Question
If during a schedule update, the critical path changed, this can be attributed to
A change in the logic.
A change in the calendar of some activities.
A near-critical path became longer than the previous critical path.
All of the other answers.
The critical path became shorter than a near-critical path.
A change in the logic.
A change in the calendar of some activities.
A near-critical path became longer than the previous critical path.
All of the other answers.
The critical path became shorter than a near-critical path.
Explanation / Answer
During the schedule update, the critical path can change if :
- The current near critical path becomes longer than the original critical path
- The current critical path becomes shorter than the near critical path
- If there is any change in logic which changes the precedence and logic
- If there is a change in the calendar and completion times of some of the activities
As all of these can be the reasons, the answer is Option D : All of the other answers