The following chart was prepared at the beginning of a HRM (Human Resource Management) crash hiring project. The project begins with two activities: Assemble interview team (A) and Budget resources (B). The duration, in days, follows the letter of each activity. What is the critical path? Which activities should be monitored more closely?

At the end of the first week, it was noted that activity A was completed in 2.5 days but activity B required 4.5 days. What impact does this have on the project? Are the same activities critical?

C1 12 A4 Start End G3 E4 1 U1 F1

Explanation / Answer

Q1) The various paths are -

ACI - 4+1+2 = 7 days

ADGJ - 4+5+3+1 = 13 days

BEGJ - 3+4+3+1 = 11 days

BFHJ - 3+1+5+1 = 10 days

The critical path is ADGJ

Q2) The activities that need to be monitored closely include A, D, G and J

Q3) Considering A = 2.5 days, B = 4.5 days => below are the various activities -

ACI = 2.5+1+2 = 5.5 days

ADGJ = 2.5+5+3+1 = 11.5 days

BEGJ = 4.5+4+3+1 = 12.5 days

BFHJ = 4.5+1+5+1 = 11.5 days.

With the change in the completion duration of A and B, now the critical path is BEGJ with 12.5 days duration and the critical activities are B,E,G and J.