Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A project to build a new bridge seems to be going very well since the project is

ID: 347664 • Letter: A

Question

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 68% complete. The planners were only expecting to be 55% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,418,500 and it was done for only $1,298,500. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,498,500 but was actually done for $8,998,500. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,498,500. To date they have spent $4,998,500 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)

Explanation / Answer

Table 3 Expected EV-AC PV-EV PV/AC PV/EV Task Ac % Expected EV AC PV CV SV CPI SPI A 100% 100% 1418500 1298500 1418500 120000 0 1.092 1.000 B 100% 87% 10498500 8998500 10498500 1500000 0 1.167 1.000 C 68% 55% 8498500 4998500 5778980 3500000 -2719520 1.156 0.680 Cumm Total 20415500 15295500 17695980 5120000 -2719520 1.157 0.867

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote