RUE/FALSE 7 pts each). Write'A if the statement is true and 'B' if the statement is false. 1) The network (AON) diagram is a planning method that is designed to depict the relationships 1) 2) A critical path is any sequence of activities between a project's start and finish. 3) Input measures of capacity are inherently more accurate than output measures of capacity 4) A smaller capacity cushion may be required if a process is highly capital intensive 5) A firm may preempt the expansion of competitive firms by using an expansionist capacity strategy between activities. and announcing a large capacity expansion. 6) The main objective of Theory of Constraints is to eliminate all of the bottlenecks from the process. 7) The drum-buffer-rope method is a practical application of steps in the Theory of Constraints 8) Line balancing strives to create workstations so that the capacity utilization for the bottleneck is much higher than for the other workstations in the line. 9) In a lean system, large inventories are not considered a type of waste, because they can prevent operator idle and wait times. 10) A five S program includes the activities of "simplify and "system.Explanation / Answer
1) The network (AON) diagram is a planning method that is designed to depict the relationships between activities.
Answer: (A) - True
2) A critical path is any sequence of activities between a project’s start and finish.
Answer: (B) - False
3) Input measures of capacity are inherently more accurate than output measures of capacity.
Answer: (B) - False
4) A smaller capacity cushion may be required if a process is highly capital intensive.
Answer: (A) - True
5) A firm may preempt the expansion of competitive firms by using an expansionist capacity strategy and announcing a large capacity expansion.
Answer: (A) - True
6) The main objective of Theory of Constraints is to eliminate all of the bottlenecks from the process.
Answer: (B) - False
7) The drum-buffer-rope method is a practical application of steps in the Theory of Constraints.
Answer: (A) - True
8) Line balancing strives to create workstations so that the capacity utilization for the bottleneck is much higher than for the other workstations in the line.
Answer: (B) - False
9) In a lean system, large inventories are not considered a type of waste, because they can prevent operator idle and wait times.
Answer: (B) - False
10) A five S program includes the activities of “simplify” and “system.”
Answer: (B) - False