elp Save&ExitSubmit; Check my work Problem 8-12 I assembly system and a. An output of 675 units per shift (7.50 hours) is desired for a new processing system. The system requires product to pass through four stations where the work content at each station is 28 seconds. What is the required cycle time for such a system? (Round your answer to the nearest whole number.) Cycle time seconds b. How efficient is your system with the cycle time you calculated? (Round your answer to the nearest wihole number) EfficiencyExplanation / Answer
a) Cycle Time Required= Total Time Taken/ Total Output = 7.5 * 60 * 60 /675 = 40 sec/unit
b) Activity time on each work station = 28 sec
Activity time on 4 workstation = 28 * 4 = 112 sec
Present Cycle Time = Activity time on 4 workstation = 112 sec
Efficiency = Reduction/Required = 64.28% more efficient
Please like and provide your reviews in comments. :-)
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.