What type of work best characterizes the following statements? Label each statem
ID: 349152 • Letter: W
Question
What type of work best characterizes the following statements? Label each statement as a portfolio, program, project, or operations. Some statements may have multiple titles.
1
Let’s schedule a meeting of all project managers to prepare for implementation
2
The Steering Committee is meeting tomorrow to prioritize work for next fiscal year.
3
The work has a beginning and end date.
4
Our department handles phone orders and keeps the customers happy.
5
We need to have a good set of processes to manage our work
6
Our organization has changed because of a recent re-organization
7
My company says I am managing the work, but I think I am really more of a coordinator.
8
We have been asked to create a new deliverable but it is too small for a project
9
I think we will be more successful if we break this effort into a dozen or more parts.
10
It seems like we answer questions from angry customers all day.
11
This project is so big I don’t know how we will ever get it done
12
I need a charter and schedule before I start this work
1
Let’s schedule a meeting of all project managers to prepare for implementation
2
The Steering Committee is meeting tomorrow to prioritize work for next fiscal year.
3
The work has a beginning and end date.
4
Our department handles phone orders and keeps the customers happy.
5
We need to have a good set of processes to manage our work
6
Our organization has changed because of a recent re-organization
7
My company says I am managing the work, but I think I am really more of a coordinator.
8
We have been asked to create a new deliverable but it is too small for a project
9
I think we will be more successful if we break this effort into a dozen or more parts.
10
It seems like we answer questions from angry customers all day.
11
This project is so big I don’t know how we will ever get it done
12
I need a charter and schedule before I start this work
Explanation / Answer
Answer:
1
Let’s schedule a meeting of all project managers to prepare for implementation: program
2
The Steering Committee is meeting tomorrow to prioritize work for next fiscal year. : program
3
The work has a beginning and end date. : project
4
Our department handles phone orders and keeps the customers happy. : operations
5
We need to have a good set of processes to manage our work. : portfolio
6
Our organization has changed because of a recent re-organization. : program. : operations
7
My company says I am managing the work, but I think I am really more of a coordinator..: program
8
We have been asked to create a new deliverable but it is too small for a project. : operations
9
I think we will be more successful if we break this effort into a dozen or more parts. : program
10
It seems like we answer questions from angry customers all day.: operations
11
This project is so big I don’t know how we will ever get it done.: Program
12
I need a charter and schedule before I start this work. : Project
1
Let’s schedule a meeting of all project managers to prepare for implementation: program
2
The Steering Committee is meeting tomorrow to prioritize work for next fiscal year. : program
3
The work has a beginning and end date. : project
4
Our department handles phone orders and keeps the customers happy. : operations
5
We need to have a good set of processes to manage our work. : portfolio
6
Our organization has changed because of a recent re-organization. : program. : operations
7
My company says I am managing the work, but I think I am really more of a coordinator..: program
8
We have been asked to create a new deliverable but it is too small for a project. : operations
9
I think we will be more successful if we break this effort into a dozen or more parts. : program
10
It seems like we answer questions from angry customers all day.: operations
11
This project is so big I don’t know how we will ever get it done.: Program
12
I need a charter and schedule before I start this work. : Project