Question 1 options: MS.51 An office furniture manufacturer needs to calculate ma
ID: 349457 • Letter: Q
Question
Question 1 options:
MS.51 An office furniture manufacturer needs to calculate material requirements for one of its most popular office chairs. The graphic above shows the bill of material for this item. Below is the MRP table for the top-level assembly (the chair):
Based on the information in the "Chair" table above, what are the Net Requirements in the week of 8/15?
What are the Planned Order Releases in the week of 9/5?
What are the Scheduled Receipts in the week of 9/19?
What is the Projected On-Hand Inventory quantity in the week of 9/26?
Chair Final Assembly 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 Gross Requirements 300 300 400 400 400 400 400 400 300 Scheduled Receipts 240 480 480 Projected On-Hand Inv. 225 Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) 1 Lot Size 120 Bill of Material for Chair Chair Final Assembly Base Assembly (1 required) (other parts...) Caster (other parts...) (5 required)Explanation / Answer
Chair Final Assembly 8/1 8/8 8/15 8/22 8/29 5/9 12/9 9/19 Gross Requirements 300 300 400 400 400 400 400 400 Scheduled Receipts 240 480 480 1560 360 Projected On-Hand Inv. 225 55 15 Net Requirements 165 465 865 785 1185 1105 1450 -15 Planned Order Receipts Planned Order Releases 1560 360 360 Lead Time (in weeks) 1 Lot Size 120 Based on the information in the "Chair" table above, what are the Net Requirements in the week of 8/15? 865 chairs What are the Planned Order Releases in the week of 9/5? 1560 chairs What are the Scheduled Receipts in the week of 9/19? 480 chairs What is the Projected On-Hand Inventory quantity in the week of 9/26? 75 chairs