value 10.00 points Problem 6-2 Company Z is just starting to make a brand new pr
ID: 351821 • Letter: V
Question
value 10.00 points Problem 6-2 Company Z is just starting to make a brand new product they have never made before. They have completed two units so far. The first unit took 12 hours to complete and the next unit took 11 hours. Based only on this information, what would be the estimate of the learning percentage in this process? (Round your answer to 1 decimal place.) inite l amn arraige References eBook & Resources Worksheet Difficulty: Basic Problem 6-2 Learning Objective: 06-01 Understand what a leaming curve is and where learning curves are applicableExplanation / Answer
Learning percentage= (Unit 2/Unit 1)*100= (11/12)*100
91.67%
According to this hypothesis, the time per unit diminishes at a steady rate each time the yield doubles.