> Moving to another question will save this response K e Question 9 of 22 estion

ID: 352804 • Letter: #

Question

> Moving to another question will save this response K e Question 9 of 22 estion 9 1 points Save Answer You have decided to apply resource leveling to a project, due to a critically required resource being available only at certain times. Which of the following will likely be true? Resource leveling can often cause the original critical path to change. Resource leveling will overallocate resources to schedule the project before the deadline Resource leveling will never alter the original critical path. Resource leveling will require additional resources to complete the project. 0 0 A Moving to another question will save this response.

Explanation / Answer

Since, in this technique the start and end dates are adjusted based on the resource constraints, it may eventually change the original critical path.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote