14. Assume the following supply chain executed in order on a daily basis. The fi
ID: 353832 • Letter: 1
Question
14. Assume the following supply chain executed in order on a daily basis. The finished product shipping to the warehouse requires one part from Factory A and one part from Factory B. Factories A and B operate in parallel and supply Factory C. The warehouse has the constraint of Quantity Shipped into the Warehouse Quantity Shipped Out of the Warehouse. The "Truck Factory to WH" must have a capacity of at least_ Truck WH to Store," must have a capacity of at least units. units and Factory A 30 Factory B 35 Truck Factory to WH ?? Warehouse 40 Truck WH to Store ?? Store 30Explanation / Answer
Factory A generates 30 parts and factory B generates 35 parts.Both operates in parallel and supply to factory C.Now using A and B 30 finished product can be produce as finished product requires 1 part of Factory A and 1 part of factory B.And quantity shipped into warehouse = quantity shipped out of the ware house.So Truck factory to warehouse must have capacity of atleast 30 units. and truck ware house to store also must have capacity of atleast 30 units.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.