Each unit of A is composed of one unit of B, two units of C, and one unit of D.
ID: 355006 • Letter: E
Question
Each unit of A is composed of one unit of B, two units of C, and one unit of D. C is composed of two units of D and three units of E. Items A, C, D, and E have on-hand inventories of 25, 20, 40, and 40 units, respectively. Item B has a scheduled receipt of 15 units in Period 1, and C has a scheduled receipt of 50 units in Period 1. Lot-for-lot (L4L) is used for Items A and B. Item C requires a minimum lot size of 60 units. D and E are required to be purchased in multiples of 110 and 60, respectively. Lead times are one period for Items A, B, and C, and two periods for Items D and E. The gross requirements for A are 40 in Period 2, 30 in Period 5, and 45 in Period 8.
Find the planned order releases for all items. (Leave no cells blank - be certain to enter "0" wherever required.)
OH = 25
LT = 1
SS = 0
Q = L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item B
OH = 0
LT = 1
SS = 0
Q = L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item C
OH = 20
LT = 1
SS = 0
Q = 60 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item D
OH = 40
LT = 2
SS = 0
Q = 110 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item E
OH = 40
LT = 2
SS = 0
Q = 60 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases
Explanation / Answer
Solution :
A, LT - 1, Lot - L4L On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 0 40 0 0 30 0 0 45 115 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 25 25 0 0 0 0 0 0 0 Net requirements 0 15 0 0 30 0 0 45 Planned order receipts 0 15 0 0 30 0 0 45 Planned order releases 15 0 0 30 0 0 45 0 B, LT - 1, Lot - L4L On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 15 0 0 30 0 0 45 0 90 Scheduled Receipts 15 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 Net requirements 0 0 0 30 0 0 45 0 Planned order receipts 0 0 0 30 0 0 45 0 Planned order releases 0 0 30 0 0 45 0 0 C, LT - 1, Lot - MIN 60 On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 30 0 0 60 0 0 90 0 180 Scheduled Receipts 50 0 0 0 0 0 0 0 Projected On Hand 20 40 40 40 40 40 40 10 10 Net requirements 0 0 0 20 0 0 50 0 Planned order receipts 0 0 0 60 0 0 60 0 Planned order releases 0 0 60 0 0 60 0 0 D, LT - 2, Lot - 110 On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 15 0 120 30 0 120 45 0 330 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 40 25 25 15 95 95 85 40 40 Net requirements 0 0 95 15 0 25 0 0 Planned order receipts 0 0 110 110 0 110 0 0 Planned order releases 110 110 0 110 0 0 0 0 E, LT - 2, Lot - 60 On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 0 0 180 0 0 180 0 0 360 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 40 40 40 40 40 40 40 40 40 Net requirements 0 0 140 0 0 140 0 0 Planned order receipts 0 0 180 0 0 180 0 0 Planned order releases 180 0 0 180 0 0 0 0Related Questions