400 products are required per week. The operation runs 8 hours, 5 days per week.

ID: 355641 • Letter: 4

Question

400 products are required per week. The operation runs 8 hours, 5 days per week. The assembly steps and times for this product are given below. Answer the following 3 questions. Wash Dry Box Grind WeldPaint Time required 4 minutes 3 minutes I minutes 5 minutes 3 minutes 2 minutes 3 minutes Task Wash Box Weld Assemble Paint Grind 12. Refer to the above information: what is the workstation cycle time? a. 4 minutes b. 5 minutes c. 6 minutes d. None of the above You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes and the sum of all that tasks required on the line is 25 minutes. Which of the following is the correct valuc for the resulting line's efficiency? a. 0.500 b. 0.833 c. 0.973 d. 0.990 e. None of the above 15. 13. Refer to the above information: What is the Theoretical Number of Workstations? a. 3 d. None of the above Which of the following is a basic type of production layout format? a. Process flow diagram b. Workcell Center c. Systematic plan d. Simo charts e. Manufacturing cell 16. Which of the following basic types of process structures is one which similar equipment or functions are grouped together? a. Project b. Workcenter c. Manufacturing cell d. Assembly line 14. Which of the following refers to the physical presence of the customer in a service system? a. Creation of the service b, Customer contact c. Intermittent production d. Continuous production e. None of the above 17.

Explanation / Answer

12) Cycle time = Available time / Demand = 8 * 60 * 5 / 400 = 6 min

13) Theoritical Workstation = Total processing time / Cycle Time = (4+3+1+5+3+2+3) / 6 = 3.5 ~ 4 numbers

14) C

15) Efficiency = Total processing time / ( no of workstations * cycle time) = 25 / ( 6* 5) = 83.33%