One unit of A is composed of two units of B and three units of C. Each B is comp

ID: 355780 • Letter: O

Question

One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 15, 50, 45, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 45, 100, and 100, respectively, to be purchased. B has scheduled receipts of 30 units in Period 1. No other scheduled receipts exist. Lead times are one period for Items A, B, and D, and two periods for Items C, E, and F. Gross requirements for A are 15 units in Period 1, 15 units in Period 2, 60 units in Period 6, and 50 units in Period 8.


Find the planned order releases for all items. (Leave no cells blank - be certain to enter "0" wherever required.)


Period 1 2 3 4 5 6 7 8 Item A
OH = 15
LT = 1
SS = 0
Q = L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item B
OH = 50
LT = 1
SS = 0
Q = L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item C
OH = 45
LT = 2
SS = 0
Q = L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item D
OH = 25
LT = 1
SS = 0
Q = 45 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item E
OH = 0
LT = 2
SS = 0
Q = 100 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item F
OH = 0
LT = 2
SS = 0
Q = 100 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases

Explanation / Answer

Solution :

A, LT - 1, Lot - L4L On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 15 15 0 0 0 60 0 50 140 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 15 0 0 0 0 0 0 0 0 Net requirements 0 15 0 0 0 60 0 50 Planned order receipts 0 15 0 0 0 60 0 50 Planned order releases 15 0 0 0 60 0 50 0 B, LT - 1, Lot - L4L On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 30 0 0 0 120 0 100 0 250 Scheduled Receipts 30 0 0 0 0 0 0 0 Projected On Hand 50 50 50 50 50 0 0 0 0 Net requirements 0 0 0 0 70 0 100 0 Planned order receipts 0 0 0 0 70 0 100 0 Planned order releases 0 0 0 70 0 100 0 0 C, LT - 2, Lot - L4L On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 45 0 0 0 180 0 150 0 375 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 45 0 0 0 0 0 0 0 0 Net requirements 0 0 0 0 180 0 150 0 Planned order receipts 0 0 0 0 180 0 150 0 Planned order releases 0 0 180 0 150 0 0 0 D, LT - 1, Lot - 45 On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 0 0 180 0 150 0 0 0 330 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 25 25 25 25 25 10 10 10 10 Net requirements 0 0 155 0 125 0 0 0 Planned order receipts 0 0 180 0 135 0 0 0 Planned order releases 0 180 0 135 0 0 0 0 E, LT - 2, Lot - 100 On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 0 0 180 0 150 0 0 0 330 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 20 20 70 70 70 70 Net requirements 0 0 180 0 130 0 0 0 Planned order receipts 0 0 200 0 200 0 0 0 Planned order releases 200 0 200 0 0 0 0 0 F, LT - 2, Lot - 100 On Hand 1 2 3 4 5 6 7 8 Total Gross Requirements 0 0 360 70 300 100 0 0 830 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 40 70 70 70 70 70 Net requirements 0 0 360 30 230 30 0 0 Planned order receipts 0 0 400 100 300 100 0 0 Planned order releases 400 100 300 100 0 0 0 0