assembly operation at a furniture factory, six employes assembled an average of

ID: 355831 • Letter: A

Question

assembly operation at a furniture factory, six employes assembled an average of 450 standard dining per five-day week. What is the labor productivity of this operation? chairs/worker/day C) 20 chairs/worker/day 60 chairs/worker/day 15 chairs/worker/day 33) Reducing inefficiencies will increase a firm's profitability A) True B) False 34) Operations management is about: A) improving the way that we and/or others do their work. B) dealing with customer feedback. C) working harder D) doing away with work. 35) The Toyota Production System can be represented in the shape of a A) pyramid B) box C) boat D) house 36) A patient spent 25 minutes waiting in the reception area before seeing a doctor. The visit with the doctor lasted 5 minutes. What is the value-added percentage of the patient? A) 8096B) 17% C) 83%D) 20% 37) Cycle time is the same as lead time. A) True B) False 35) For the purpose of process analysis, which of the following is NOT measured in an appropriate flow unit for analyzing the operation of a hair salon? A) Monthly sales figures B) The dollar value of haircare products sold per day C) Number of customers served per day D) Number of stylists working each day 39) Lean operations is about reducing two forms of waste, wastedand wasted A) inventory, time B) inventory, flow time c) inventory, capacity D) capacity, flow time 40) C&A; Fast Food has four activities in serving a customer: greet customer, take order, process order, and deliver order. Each activity is staffed by one employee (for a total of four employees). The processing time for each activity is given as follows: Processing time per customer Activity Greet customer Take order Process order Deliver order seconds seconds 0 seconds 5 seconds

Explanation / Answer

32) Six employees assemble 450 dining table chairs per five days week.

So output = 450 chairs

Labor input = 6 workers

Work day = 5 days

Labor productivity = output / labor input / work days

= 450 chairs / 6 workers / 5 days

= 75 chairs per workers / 5days

= 15 chairs / workers / day

So the answer is option E