What are Level of Effort tasks?
A) Tasks with higher risk
B) Tasks that cannot be measured with a percent complete
C) Tasks that can be measured with a percent complete
Which of the following is not a purpose of the project charter?
A) Define the detailed product design requirements
B) Provide a description of the project
C) Define high level risk Incorrect Response D) None of the above
D) Tasks with measurable status
Which of the following is part of the Scope Planning Documents?
A) Statement of Work
B) Risk Management Plan
C) Earned Value Management Plan
D) WBS
Which of the following is not a purpose of the project charter?
A) Define the detailed product design requirements
B) Provide a description of the project
C) Define high level risk Incorrect Response
D) None of the above
Explanation / Answer
1. What are Level of Effort tasks?
option B Tasks that cannot be measured with a percent complete
level of effort are support activities which needs to be done to support other important activities and cannot be measured with percent complete.
2. Which of the following is part of the Scope Planning Documents?
option C Earned Value Management Plan
all the other options are important part of Scope Planning, like statement of work, WBS and risk management.
3. Which of the following is not a purpose of the project charter?
option A, Define the detailed product design requirements
project charter is a brief guide to the project details and description and people working in it and brief timelines for the project. It does not include detailed product design