Project managers can identify risks by learning and understanding the cause and

ID: 358542 • Letter: P

Question

Project managers can identify risks by learning and understanding the cause and effect relationships that bear on risk events. All of the following approaches rely upon an understanding of cause and effect relationships to identify risks EXCEPT:

?

perform a Monte Carlo analysis

develop a flow chart that shows how people, materials or data flow from one person or location to another

conduct a root cause analysis

understand trigger conditions, or circumstances under which a risk strategy or risk action will be invoked

a.

perform a Monte Carlo analysis

b.

develop a flow chart that shows how people, materials or data flow from one person or location to another

c.

conduct a root cause analysis

d.

understand trigger conditions, or circumstances under which a risk strategy or risk action will be invoked

Explanation / Answer

a. Perform a Monte Carlo analysis

As remaining approaches rely upon an understanding of cause and effect relationships to identify risks.