Bisutti Cams is producing its Racing Camshaft models RC1 and RC2. It is a three-
ID: 361738 • Letter: B
Question
Bisutti Cams is producing its Racing Camshaft models RC1 and RC2. It is a three-state process that involves collecting the appropriate items from inventory, assembling, and then inspecting them. Bisutti Cams is making its labor estimates for the next four quarters for the collecting, assembling and inspecting operations. The RC1 requires 5 hours of labor and the RC2 requires 2 hours. The collecting process uses 20% of its labor resources, the assembling uses 70%, and the inspecting uses 10%. The production schedule for the next four quarters is given below.
Calculate the labor hours required in the collecting, assembling, and inspecting processes for the next four quarters.
Endproduct 1 Quarter
2 3 4
RC1 100 120 200 140
RC2 200 250 150 100
Explanation / Answer
Quarter End Product 1 2 3 4 RC1 100 120 200 140 Collecting hours 100 120 200 140 Assembling hours 350 420 700 490 Inspecting hours 50 60 100 70 Quarter End Product 1 2 3 4 RC2 200 250 150 100 Collecting hours 80 100 60 40 Assembling hours 112 140 84 56 Inspecting hours 40 50 30 20
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.