You need to develop a labor time estimate for a customer order of 20 network installations. it is estimated that the first installation will require 60 hours of labor and a learning curve of 90 percent is expected.

a. How many labor hours are required for the fifteenth installation?

b. How many labor- hours are required for the twentieth installation?

c. How many labor-hours are required to complete all 20 installations?

d. If the average labor cost is $32, what is the total labor cost for installing the networks

Explanation / Answer

We will use Standard Learning Curve table to find answers to the questions

Given are :

Time required for 1st installation = 60 hours

Learning curve = 90 percent

Accordingly ,

Time required for 15th installation using learning curve table = 39.75 hours

Time required for 20th installations as per learning curve table = 38.05 hours

Total labour hours required to complete all 20 installations = 876.47 hours

Total labour cost for installing 20 networks = $32 / hour x 876.47 hours = 28047.04 hours