Eva's company makes tables with three components as shown in the accompanying product structure tree. This company wants to ship 50 units at the end of 4 weeks, 75 at the beginning of 8 weeks. 50 wood sections are scheduled at the beginning of day2. There is a balance of braces-30 and legs-60. Lead time in weeks is mentioned for various quantity in the below table. The product tree diagram is also shown a) Prepare a Master Production schedule a) Prepare a material requirement plan using lot-for-lot ordering. Table Wood sections (2) Braces (3) Legs (4) Quantity 1-50 Lead time 1 week 2 weeks 101-1503

Explanation / Answer

* Note: 50 is required at the end of 4th week i.e. at the beginning of 5th week.

Also, we assume that the lead time chart is applicable to Table production as well.

MRP explosion

* 50 units will be received on day 2 i.e. in week 1

Table 1 2 3 4 5 6 7 8 Gross Requirement 50* 75 Scheduled Receipt 0 0 0 0 0 0 0 0 Projected on hand 0 0 0 0 0 0 0 0 0 Net Requirement 0 0 0 0 50 0 0 75 MPS 0 0 0 50 0 75 0 0