The following represents a project that should be scheduled using CPM: 10 IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a m 14 3 5 2 5 4 6 1 2 C,D 3 5 D,E 1 2 F,G 2 5 b. What is the critical path? O B-E-G-H O A-C-F-H O A-D-F-H O A-D-G-H c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 22 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.) ProbabilityExplanation / Answer
b. We need to compute the expected time of each activity. Expected time = (a+4m+b)/6
Expected duration of each path:
The highest duration is 20.167 and hence A-D-F-H is the critical path.
c. Expected project completion time = duration of the critical path (as calculated above) = 20.167 days
d. Variance = ((pessimistic activity time estimate - optimistic activity time estimate)/6)^2
Variance of critical path = 1+1.361+0.444+0.444 = 3.25
z = (22 - 20.167)/(3.25^2)
= 1.02
Thus probability associated with z value of 1.02 = 0.8461 (from Z table)
Activity a m b Expected time = (a+4m+b)/6 A 1.00 4 7.00 4.00 B 3.00 5.00 10.00 5.50 C 2.00 5.00 8.00 5.00 D 4.00 6.00 11.00 6.50 E 1.00 2.00 3.00 2.00 F 3.00 5.00 7.00 5.00 G 1.00 2.00 6.00 2.50 H 2.00 5.00 6.00 4.67Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.