Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A (not-so-well maintained machine) machine is down roughly 40% of the time. One

ID: 364827 • Letter: A

Question

A (not-so-well maintained machine) machine is down roughly 40% of the time. One operator is assigned to service four identical such machines. Each machine can produce 60 widgets/hr if running (i.e. not completely idle). The operator is paid $10.00/hr and each machine costs $20.00/hr for power and supplies.

a) What is the actual production for the four machines supervised by one operator for an 8hour shift given the above conditions?

b) What is the unit cost for each widget?

c) Since there is so much lost production due to idle time, management is considering hiring another worker to assist the first operator in servicing these four machines.

There are two approaches or choices:

Assign machines #1 and #2 to the first operator and machines #3 and #4 to the second operator

Or have both operators help each other and service all four machines as needed

      Which choice is best, i.e. lowest unit cost?

Explanation / Answer

Calculate the probability and idle time (hours)

a) Actual production = (4*8-2.76-2.46-0.61)*60 = 1,570.2 parts

b) Total cost = machine cost + operator cost = 4*8*20+8*10 = $ 720

Unit cost = 720/1570.2 = $ 0.459 per unit

c)

Option 1 - Assign machines #1 and #2 to the first operator and machines #3 and #4 to the second operator

Lost time occurs only if both machines of an operator are down. Probability of this event = 2C0*0.42*0.60 = (2!/0!2!)**0.42*0.60 = 0.16. Total lost hours for each operator (machine 1 and 2 or 3 and 4) = 8*0.16 = 1.28

Production = (2*8-1.28)*60 = 883.2 units

Total cost of each split (machine 1&2 or 3&4) = (2*20+10)*8 = 400

Unit cost = 400/883.2 = $ 0.453 per unit

Option 2 - Both operators help each other and service all four machines as needed

Increase in production = (2.76+0.1536*8+0.0256*8)*60= 251.6 units

New total cost = 720+80 = 800

New unit cost = 800/(1570.2+251.6) = $ 0.439 per unit

Unit cost of option 2 is lower. Therefore the best option is option 2 (both operators help each other and service all four machines as needed)

Up Down Probability Idle time 4 0 4!(.40 )(.64 )/0!4! = 0.1296 0 3 1 4!(.41 )(.63 )/1!3! = 0.3456 0 2 2 4!(.42 )(.62 )/2!2! = 0.3456 0.3456*8*1=2.76 1 3 4!(.43 )(.61 )/3!1! = 0.1536 0.1536*8*2=2.46 0 4 4!(.44 )(.60 )/4!1! = 0.0256 0.0256*8*3=0.61