D (2) F (2) 23. Given the above bill of materials, if the demand for product A i
ID: 365326 • Letter: D
Question
D (2) F (2) 23. Given the above bill of materials, if the demand for product A is 50 units, what will be the gross requirement for component D? (a) 50 (b) 100 (c) 150 (d) 200 (e) 300 Present Method X Proposed Method DATE SHEET NO. 1-OF-1. PROCESS CHART SUBJECT CHARTED Hamburger Assembly Process DEPARTMENT CHART BY DIST TIME IN CHART SYMBOLS PROCESS DESCRIPTION IN FEET MINS. Meat Patty in Storage .05-1. pnl Dy|-Transfer to Broiler 2.5 Broiler 5 ] D [Visual Inspection Transfer to Rack 1.0 O5 15 DV Temporary Storage 1O CD perl DIObta in Buns,Lettuce, etc 0-1 G( [Assemble Order 5-1-0 5 1 D D|Place-in-Finish Rack 3.5 value-added time-Operation time/Total time TOTALS (2.50+.20)/3. operation; = transport; E] = inspect; 15 = 85.7% delay;V-storage.Explanation / Answer
So 1 unit of A required 3 units of D.
Hence 50 units of A requires 3*50 = 150 units of D.
Option C
Requires 1 unit A 1 unit B and 1 unit C 2 units D 1 unit D effective 3 units DRelated Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.