2. A maintenance group aims to improve the effectiveness of its repair work. The

ID: 365483 • Letter: 2

Question

2.

A maintenance group aims to improve the effectiveness of its repair work. The group therefore monitors the number of maintenance requests that require a second visit to complete the repair. On any given week the maintenance group responds to 200 maintenance requests. The following table summarizes the number of those maintenance requests that required a second visit in the last five weeks.

Week Number  1 2 3 4 5

Number of those maintanance requests that required a second visit

6 8 9 7 3

What type of control chart should be used here?

Select one:

a. p-chart

b. run test

c. c-chart

d. mean chart

e. range chart


e maintenance group aims to improve the efectivenes of its repair work. The group therofore moniors the mumber of m secand visit to complete the repair On any given week the maintenance group responds to 200 maintenance number of those maintenance requests that required a second visit in the last firve weeks aintenance requests that requre a requests The folowing table summarizes the Number 2E46 Number of those maintanance requests that required a What type af control chart should be used here? Select one a.p-chart b nun test d mean chart range

Explanation / Answer

P outlines are utilized to screen the extent of nonconforming units of a process on a sample of tests taken from the process at given circumstances (hours, shifts, days, weeks, months, and so on.). Initially, the tests are performed to determine the proportion of nonconforming customers. After that, a sample is taken to estimate if there are some customers who have visited again for the maintenance.