Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A390 Operations Management all 2017 2. [Lot Sizing in Material Requirement Syste

ID: 365861 • Letter: A

Question

A390 Operations Management all 2017 2. [Lot Sizing in Material Requirement System (MRP) a job as a production planner at Honda Automotive Assembly Plant in Lincoln, Alabama. His first task on the job training is to review the master production plan shown below: (Initial in Lead time 1 week, Holding cost $1 per unit per week.) Part: Period Gross requirements 100170 200 150 0 1200 Develop an ordering plan and costs for this plant using the following techniques. a) Develop the lot-for-lot MRP table and cakculate the total relevant costs. Part Lot-for-Lot Lot Siz Gross requirements Scheduled receipts Projected available (Be Period 150 Net requirements Planned orderreceipts Planned order releases Lead time 1 wk Lot size Holding Cost Ordering Cost Total Cost = b) Develop the Economic Order Quantity (EOQ) lot sizing technique. (Assume EOQ 200) Period Part: EOQ Lot Siz 100 170 200 150 0 1200 Scheduled receipts Projected availa ble (Beg.) On hand (End of period) Net requirements Planned order receipts lanned order releases Lead time 1wk Lot size- Ordering Cost Total Cost Holding Cost Develop the Periodic Order Quantity (POQ) lot sizing technique. (Assume POQ Interval 2 weeks) Perioc Part POQ Lot Siz Gross requirements Scheduled receipts Projected available (Beg) 150 1001170|200 | 150 0 120 1 0 On hand (End of period) Net requirements Planned order receipts Planned order releases 1 wk Lot sizes Lead time Total Cost = Holding Cost = Ordering Cost = (d) Among the three lot sizing techniques above, which has the lowest cost?

Explanation / Answer

Part a

Item:
OH = 150
LT = 1
SS = 0
Q = L4L

1

2

3

4

5

6

7

Gross Req.

100

170

200

150

0

120

0

Scheduled receipts

Projected-on-hand

150

50

0

0

0

0

0

Inv. On hand (ending inv)

50

0

0

0

0

0

0

Net Requirement

0

120

200

150

0

120

0

Planned order Receipts

120

Planned order releases

120

200

150

120

Total Inventory carried

50

Holding cost

50*1 = 50

Number of Orders

4

Ordering Cost

4*200 = 800

Total Cost

50 + 800 = 850

Part b

Item:
OH = 150
LT = 1
SS = 0
Q = EOQ = 200

1

2

3

4

5

6

7

Gross Req.

100

170

200

150

0

120

0

Scheduled receipts

Projected-on-hand

150

50

80

80

130

130

0

Inv. On hand (ending inv)

50

80

80

130

130

10

10

Net Requirement

0

120

120

70

0

0

0

Planned order Receipts

200

200

200

0

0

0

Planned order releases

200

200

200

Total Inventory carried

50+8+80+130+ 130 + 10 +10

= 490

Holding cost

490*1 = 490

Number of Orders

3

Ordering Cost

3*200 = 600

Total Cost

490 + 600 = 1090

Part C

Item:
OH = 150
LT = 1
SS = 0
Q = POQ = 2 weeks

1

2

3

4

5

6

7

Gross Req.

100

170

200

150

0

120

0

Scheduled receipts

Projected-on-hand

150

50

200

0

0

0

0

Inv. On hand (ending inv)

50

200

0

0

0

0

0

Net Requirement

0

120

0

150

0

120

0

Planned order Receipts

320

0

150

0

120

0

Planned order releases

320

150

120

Total Inventory carried

50+200 = 250

Holding cost

250*1 = 250

Number of Orders

3

Ordering Cost

3*200 = 600

Total Cost

250+600 = 850

Part a

Item:
OH = 150
LT = 1
SS = 0
Q = L4L

1

2

3

4

5

6

7

Gross Req.

100

170

200

150

0

120

0

Scheduled receipts

Projected-on-hand

150

50

0

0

0

0

0

Inv. On hand (ending inv)

50

0

0

0

0

0

0

Net Requirement

0

120

200

150

0

120

0

Planned order Receipts

120

Planned order releases

120

200

150

120

Total Inventory carried

50

Holding cost

50*1 = 50

Number of Orders

4

Ordering Cost

4*200 = 800

Total Cost

50 + 800 = 850

Part b

Item:
OH = 150
LT = 1
SS = 0
Q = EOQ = 200

1

2

3

4

5

6

7

Gross Req.

100

170

200

150

0

120

0

Scheduled receipts

Projected-on-hand

150

50

80

80

130

130

0

Inv. On hand (ending inv)

50

80

80

130

130

10

10

Net Requirement

0

120

120

70

0

0

0

Planned order Receipts

200

200

200

0

0

0

Planned order releases

200

200

200

Total Inventory carried

50+8+80+130+ 130 + 10 +10

= 490

Holding cost

490*1 = 490

Number of Orders

3

Ordering Cost

3*200 = 600

Total Cost

490 + 600 = 1090

Part C

Item:
OH = 150
LT = 1
SS = 0
Q = POQ = 2 weeks

1

2

3

4

5

6

7

Gross Req.

100

170

200

150

0

120

0

Scheduled receipts

Projected-on-hand

150

50

200

0

0

0

0

Inv. On hand (ending inv)

50

200

0

0

0

0

0

Net Requirement

0

120

0

150

0

120

0

Planned order Receipts

320

0

150

0

120

0

Planned order releases

320

150

120

Total Inventory carried

50+200 = 250

Holding cost

250*1 = 250

Number of Orders

3

Ordering Cost

3*200 = 600

Total Cost

250+600 = 850

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote