Closing Case: Disaster at Denver International Airport
One good way to learn how to develop successful systems is to review past failures. One of the most infamous system failures is Denver International Airport’s (DIA) baggage system. When the automated baggage system design for DIA was introduced, it was hailed as the savior of modern airport design. The design relied on a network of 300 computers to route bags and 4,000 cars to carry luggage across 21 miles of track. Laser scanners were to read bar-coded luggage tags, while advanced scanners tracked the movement of toboggan-like baggage carts.
When DIA finally opened its doors for reporters to witness its revolutionary baggage handling system, the scene was rather unpleasant. Bags were chewed up, lost, and misrouted in what has since become a legendary systems nightmare.
One of the biggest mistakes made in the baggage handling system fiasco was that not enough time was allowed to properly develop the system. In the beginning of the project, DIA assumed it was the responsibility of individual airlines to find their own way of moving the baggage from the plane to the baggage claim area. The automated baggage system was not involved in the initial planning of the DIA project. By the time the DIA developers decided to create an integrated baggage system, the time frame for designing and implementing such a complex and huge system was not possible.
Another common mistake that occurred during the project was that the airlines kept changing their business requirements. This caused numerous issues, including the implementation of power supplies that were not properly updated for the revised system design, which caused overloaded motors and mechanical failures. Besides the power supply design problem, the optical sensors did not read the bar codes correctly, causing issues with baggage routing.
Finally, BAE, the company that designed and implemented the automated baggage system for DIA, had never created a baggage system of this size before. BAE had created a similar system in an airport in Munich, Germany, where the scope was much smaller. Essentially, the baggage system had an inadequate IT infrastructure because it was designed for a much smaller system.
DIA simply could not open without a functional baggage system so the city had no choice but to delay the opening date for more than 16 months, costing taxpayers roughly $1 million per day, which totaled around $500 million.
One problem with DIA’s baggage system was inadequate testing. Why is testing important to a project’s success? Why do so many projects decide to skip testing?
Closing Case: Disaster at Denver International Airport
One good way to learn how to develop successful systems is to review past failures. One of the most infamous system failures is Denver International Airport’s (DIA) baggage system. When the automated baggage system design for DIA was introduced, it was hailed as the savior of modern airport design. The design relied on a network of 300 computers to route bags and 4,000 cars to carry luggage across 21 miles of track. Laser scanners were to read bar-coded luggage tags, while advanced scanners tracked the movement of toboggan-like baggage carts.
When DIA finally opened its doors for reporters to witness its revolutionary baggage handling system, the scene was rather unpleasant. Bags were chewed up, lost, and misrouted in what has since become a legendary systems nightmare.
One of the biggest mistakes made in the baggage handling system fiasco was that not enough time was allowed to properly develop the system. In the beginning of the project, DIA assumed it was the responsibility of individual airlines to find their own way of moving the baggage from the plane to the baggage claim area. The automated baggage system was not involved in the initial planning of the DIA project. By the time the DIA developers decided to create an integrated baggage system, the time frame for designing and implementing such a complex and huge system was not possible.
Another common mistake that occurred during the project was that the airlines kept changing their business requirements. This caused numerous issues, including the implementation of power supplies that were not properly updated for the revised system design, which caused overloaded motors and mechanical failures. Besides the power supply design problem, the optical sensors did not read the bar codes correctly, causing issues with baggage routing.
Finally, BAE, the company that designed and implemented the automated baggage system for DIA, had never created a baggage system of this size before. BAE had created a similar system in an airport in Munich, Germany, where the scope was much smaller. Essentially, the baggage system had an inadequate IT infrastructure because it was designed for a much smaller system.
DIA simply could not open without a functional baggage system so the city had no choice but to delay the opening date for more than 16 months, costing taxpayers roughly $1 million per day, which totaled around $500 million.
Explanation / Answer
It is very common for project on a tight budget to plan and execute as little testing as possible. During project execution phases, the assumption is always that the working process shows no faults or problems, so testing is not required. But for the success of the project, this approach towards testing requirement is devastating to the project’s success if technical problems are found later during implementation. Project owners perceive the Testing as an extra cost, but the reality is that the relative cost of testing is small compared with the cost to go back and rework.
In general. It is always tempting to skip out on testing procedures to save some money, but it is a risky proposition and can lead to the project ultimate failure. Even if small project also, one should take the time to find at least one quality testing person to test the hardware and go through the specifications.