Complete the missing reasons column for the last 6 risks (except the answered on

ID: 3693040 • Letter: C

Question

Complete the missing reasons column for the last 6 risks (except the answered one) in the following table ( # 9,11,13,14 & 8)

Risk

Probability

Effects

Reason

Organizational financial problems force reductions in the project budget (7).

Low

Catastrophic

If the project budget is low, then the effect is catastrophic because organisation earn their bread by completing projects. So to earn good income for the organisation, project budget should be high.

It is impossible to recruit staff with the skills required for the project (3).

High

Catastrophic

For meeting deadlines, in the project, very good skills are required in the staffs to face new challenges coming in the project. If they are not able too recruit such kind of staff, then the effect will be catastrophic because, the Deadline will not be met, loss of huge income, and chances of permanently losing client or customer.

Key staff are ill at critical times in the project (4).

Moderate

Serious

Key staffs should be present at critical times in the project to handle unexpected situation. If they are not there, then the effect will be serious because the whole project will go into the messy situation and others will not know how to handle it.

Faults in reusable software components have to be repaired before these components are reused. (2).

Moderate

Serious

Faults in reusable components have to be fixed before they are reused because, these faults will create a further issue and because of these faults, new faults will appear causing unexpected problems which is a very serious issue. These faults can also lead to failure

Changes to requirements that require major design rework are proposed (10).

Moderate

Serious

Changes to requirements that require major design rework are proposed because the design after making changes may be very efficient. These changes must not be ignored. These changes will help us to do our work in very easy way. It may save lot of cost which has to be put into the project.

The organization is restructured so that different management are responsible for the project (6).

High

Serious

The organization should restructured so that different management are responsible for the project ,this is very efficient ,because dividing people in which they are better earn more profit.

The database used in the system cannot process as many transactions per second as expected (1).

Moderate

Serious

The database used in the system cannot process as many transactions per second as expected .This may happen due to the overload and corruption of data .This is a serious issue because we cannot work in the speed in which we expect. This will cause loss of time.

The time required to develop the software is underestimated (12).

High

Serious

Underestimating the time required to develop the software is an serious issue because unexpected problems are common in software and this may delay deadlines .

Software tools cannot be integrated (9).

High

Tolerable

Customers fail to understand the impact of requirements changes (11).

Moderate

Tolerable

Required training for staff is not available (5).

Moderate

Tolerable

As required training for staff is not available , as this causes more time to staffs to get adjusted to new platform and it delays the completion of the project.

The rate of defect repair is underestimated (13).

Moderate

Tolerable

The size of the software is underestimated (14).

High

Tolerable

Code generated by code generation tools is inefficient (8).

Moderate

Insignificant

Risk

Probability

Effects

Reason

Organizational financial problems force reductions in the project budget (7).

Low

Catastrophic

If the project budget is low, then the effect is catastrophic because organisation earn their bread by completing projects. So to earn good income for the organisation, project budget should be high.

It is impossible to recruit staff with the skills required for the project (3).

High

Catastrophic

For meeting deadlines, in the project, very good skills are required in the staffs to face new challenges coming in the project. If they are not able too recruit such kind of staff, then the effect will be catastrophic because, the Deadline will not be met, loss of huge income, and chances of permanently losing client or customer.

Key staff are ill at critical times in the project (4).

Moderate

Serious

Key staffs should be present at critical times in the project to handle unexpected situation. If they are not there, then the effect will be serious because the whole project will go into the messy situation and others will not know how to handle it.

Faults in reusable software components have to be repaired before these components are reused. (2).

Moderate

Serious

Faults in reusable components have to be fixed before they are reused because, these faults will create a further issue and because of these faults, new faults will appear causing unexpected problems which is a very serious issue. These faults can also lead to failure

Changes to requirements that require major design rework are proposed (10).

Moderate

Serious

Changes to requirements that require major design rework are proposed because the design after making changes may be very efficient. These changes must not be ignored. These changes will help us to do our work in very easy way. It may save lot of cost which has to be put into the project.

The organization is restructured so that different management are responsible for the project (6).

High

Serious

The organization should restructured so that different management are responsible for the project ,this is very efficient ,because dividing people in which they are better earn more profit.

The database used in the system cannot process as many transactions per second as expected (1).

Moderate

Serious

The database used in the system cannot process as many transactions per second as expected .This may happen due to the overload and corruption of data .This is a serious issue because we cannot work in the speed in which we expect. This will cause loss of time.

The time required to develop the software is underestimated (12).

High

Serious

Underestimating the time required to develop the software is an serious issue because unexpected problems are common in software and this may delay deadlines .

Software tools cannot be integrated (9).

High

Tolerable

Customers fail to understand the impact of requirements changes (11).

Moderate

Tolerable

Required training for staff is not available (5).

Moderate

Tolerable

As required training for staff is not available , as this causes more time to staffs to get adjusted to new platform and it delays the completion of the project.

The rate of defect repair is underestimated (13).

Moderate

Tolerable

The size of the software is underestimated (14).

High

Tolerable

Code generated by code generation tools is inefficient (8).

Moderate

Insignificant

Explanation / Answer

9) integrated tools are useful in conbining the different modules of the software. Lack of integrated tools will cost lots of time.

11) Customer failed to understand the requirement changes:- requirement changes leads to misconfigurations, which leads to performance failures. requirement changes also leads to downtime, downtime impact on revenue.

13)Defect probability may be moderate,higher or low. if the organisation underestimated the defects and assign the low capable persons to the projects leads problems in the project.

14)due to the under estimation of the project ,organisation may assign less budget to the project which leads uncertainity in the project.

8)Code generators are not sufficient in all the cases . man power is required in some situations.