In the beginning of week 1 (which corresponds to shop day 250 in the shop calend
ID: 369664 • Letter: I
Question
In the beginning of week 1 (which corresponds to shop day 250 in the shop calendar) release the order for part 100. Calculate the finish date for this part 100 on Work Center 12. What kind of problems (if any) do you anticipate the company will face in completing this order on time? Comment on the reasons for suchproblems.
Part Name: Lawn Mower 150
Part Number: 150
Drawing Number: D12X-150
ROUTING
FILE
Operation No:
Work Center
Setup Time (std hours)
Run Time/piece (Std hours)
Operation
10
12
1
0.35
Case Assembly
20
15
0.1
0.25
Inspection
30
17
0.1
0.25
Packaging
40
Store
-
-
Inventory
Part Name: Lawn Mower 150
Part Number: 150
Drawing Number: D12X-150
ROUTING
FILE
Operation No:
Work Center
Setup Time (std hours)
Run Time/piece (Std hours)
Operation
10
12
1
0.35
Case Assembly
20
15
0.1
0.25
Inspection
30
17
0.1
0.25
Packaging
40
Store
-
-
Inventory
Explanation / Answer
Processing time on workcenter 12 = run time/piece * quantity = 0.35*100 = 35 hours
Total flow time = setup time + processing time = 1 hour + 35 hours = 36 hours
Considering 8 hours working day, finish date on work center 12 = 250 + 36/8 = 254
Resource constraints could be the potential problem in completing the order on time.
Part Name: Lawn Mower 150 Part Number: 150 Drawing Number: D12X-150 ROUTING FILE Operation No: Work Center Setup Time (std hours) Run Time/piece (Std hours) Operation 10 12 1 0.35 Case Assembly 20 15 0.1 0.25 Inspection 30 17 0.1 0.25 Packaging 40 Store - - InventoryRelated Questions