Project Performance Measure

Question 1: Project Performance Measure: (Earned Value) (6 points) Given the project network and baseline information bclow, complete the Table 3 & Table 4 Questiona: Project status (SV, CV, CPI, SPI) at the end of period 4 and the end of period 8. (5 pts) Table. Network LEGEND ES ID EF SL LF SL 8 D 12 LS 2 8 8 8 4 12 12 F 15 12 3 15 7 E 10 4 59 9 3 12 Table 2. Planned value Project baseine (PV) lin $) ask DUR ES 2 | 0 2 | 0 | 400 2001 200 B6 22400 C 5 292 1500 D 4 8 12 01600 2 900 200 | 000 | 200 | 600 | 200 | 200 400 500 100 300 300 400 200 F 3 12 200 100 300 Period PV Sotal 200 200 400 700 700 500 900 800 600 400 400 200 100 300 Cumulative PV scal 200 400 800 18002 700 4600 5400

Explanation / Answer

1.(a)

End of week 4

End of week 8

1.(b)

From the final indices, it is very clear that for the entire project, at the end of week 8, EV > AC indicating a good cost performance (actual cost is lesser than EV) and EV > PV indicating a good schedule performance (faster achievement than the planned value). So, the project is 'underbudget' and 'ahead of the schedule'.

Task Budget Actual %
Complete EV
(Budget * % complete) AC PV CV
(EV - AC) SV
(EV - PV) CPI
(EV/AC) SPI
(EV/PV) A 400 100% 400 300 400 100 0 133.33% 100.00% B 2400 50% 1200 1000 800 200 400 120.00% 150.00% C 1500 33% 495 500 600 -5 -105 99.00% 82.50% D 1600 0% 0 0 0 0 0 - - E 900 0% 0 0 0 0 0 - - Cumulative totals 2095 1800 1800 295 295 116.39% 116.39%