3) An electronics company has the following MPS for Product X and the following

ID: 371871 • Letter: 3

Question

3) An electronics company has the following MPS for Product X and the following product structure Product X Weck Weck 2 Weck 3 Weck 4 Weck 5 Component A Component C MPS 10 25 30 20 20 Component B x2 Notice that Part C has a lead time of 2 weeks; the first week is spent in work center 200 and the second week in work center 300. Assume that all standard lot sizes are 20 for all parts on all work centers Calculate the capacity requirements in each work center using resource profiles procedure Item Operation Work Center Setup Hours Run Hours/Un Lead time 100 200 200 200 300 0,9 0,4 0,4 Product X of 1 Component A ofl Component B 1 of 1 Component C of 2 3,5 2 of 2

Explanation / Answer

Part B   On hand   week 1   week 2   week 3   week 4   week 5   week 6   week 7   week 8
Gross requirements       5   10   10   20   20   15   15   0
scheduled receipts               10                  
projected On hand - 20   20   15   5   5   0   0   0   0   0
Net Requirements       0   5   5   20   20   15   15   0
Planned order receipts           5   5   20   20   15   15   0
Planned order releases       5   5   20   15   15   0   0   0
Part 500       week 1   week 2   week 3   week 4   week 5   week 6   week 7   week 8
Gross requirements       5   10   10   20   20   15   15   0
scheduled receipts       10                          
projected On hand - 20   20   25   15   0   0   0   0   0   0
Net Requirements       0   0   10   20   20   15   15   0
Planned order receipts           0   10   20   20   15   15   0
Planned order releases       0   10   20   20   15   15   0   0
Part 300       week 1   week 2   week 3   week 4   week 5   week 6   week 7   week 8
Gross requirements       5   10   10   20   20   15   15   0
scheduled receipts           10                      
projected On hand - 30   30   25   25   15   0   0   0   0   0
Net Requirements       0   0   0   20   20   15   15   0
Planned order receipts           0   0   20   20   15   15   0
Planned order releases           0   20   20   15   15   0