Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Q. Develop MRP for component F. Eighty units of end item X are needed at the beg

ID: 372041 • Letter: Q

Question

Q. Develop MRP for component F.

Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed at the beginning of week 8 B(2) D(3) D(2) F(2) units per case). One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5,7). Also, there are 30 units of B and 20 units of D now on hand. Lead times for all items are a function of quantity: one week for up to 100 units, two weeks for 101 to 200 units, three weeks for 201 to 300 units, and four weeks for 301 or more units. (Leave no cells blank- be certain to enter "O" wherever required.)

Explanation / Answer

Net Req X 80 30 B 130 60 D1 240 90 D2 260 120 F 260 120 Part F      Beg. Inv. 1 2 3 4 5 6 7 8   Gross requirements 0 0 0 0 260 0 120 0 0   Scheduled receipts 0 0 0 0 0 0 0 0 0   On hand 0 0 0 0 0 0 0 0 0   Net requirements 0 0 0 0 260 0 120 0 0   Planned-order receipt 0 0 0 0 0 260 0 120 0   Planned-order release 0 0 0 0 0 260 0 120 0