1.Which of the following is NOT a step for CPM schedule? WBS Activity Relationsh
ID: 372534 • Letter: 1
Question
1.Which of the following is NOT a step for CPM schedule?
WBS
Activity Relationships
Resource Leveling
Forward pass and Backward Pass
2.A Bar Chart
Simple and easy to prepare and understand
Shows logical relationships
Is time scaled
Can be easily modified
1.A formal CPM analysis for a project shows the planned costs to date are $75,000, and the accounting department reports charges to the job of $85,000. If the reported earn value to date is $70,000, the cost and schedule status of the project are most nearly
Ahead of schedule and over budget
Behind schedule and over budget
Ahead of schedule and under budget
Behind schedule and under budget
2.Which of the following is NOT a benefit of formal schedules?
Provides time information
Estimate cost
Forces detailed thinking
Improves communication
3.Define project control and discuss the role of project updating as part of project control.
Explanation / Answer
1. The correct answer is WBS.
CPM refers to critical path method where shortest path is taken to plan the project. The steps in CPM schedule include: -