1). (a) it is the document which satisfy the order in which the project document

ID: 372963 • Letter: 1

Question

1). (a) it is the document which satisfy the order in which the project document will be used when it become necessary to resolve inconsistencies between the project documents.since it clarifies any uncertenties or confusion regarding work between the construction documents.

2( e) all of the above since the contract is legal binding agreement which is enfoceable by law, having capacity to enter into an agreement (age is above 18 with sound mind) , contract formation is an offer, acceptance, consideration and mutually intent by both the parties.

3(a) set price and terms because in purchase cycle while having purchase order we need to set forth the description, capacity, price, payment terms after analyse the demand and market price of the product .

4(e) all of the above because it affects all the factors cost and price analysis, integration and capacity of the production system, competent suppliers etc.

Explanation / Answer

. The Order of Precedence is: a. The document that specifies the order (ptriority) in which project documents will be used when it becomes necessary to resolve inconsistencies between project documents b C. d. e. The order in which project tasks should be completed The relationship that project tasks have to one anocher The ordered list (by quality) of the screened vendors for a project deliverable None of the above 38. Under which of the following conditions will a contract be regarded as a legal and binding document a. Mutual agreement b. Consideration . Contract capacity d. Legal purpose in a form provided by Law e. All of the above In the purchasing cycle, which task falls between Need Definition and Market Analysis? a. Set price and terms b. Describe/transmit need c. Preparelissue order d. Receive/inspect e. None of the above S0 Which of the following would you consider when evaluating a buy decision a Cost/price b. Supplier skills · Level ofcontrol required d. Degre of integration the purchased good or service has with the project e. All of the above . A project manager desires indirect control of the production of a project deliverable b. When there are many quality vendors available and the project manager has limited su- pervisory management resources available hen the project manager has specific technical deliverable C. W expertise in the area of the project d. a and b e b and c 32. The document that describes the details of the task in terms ofphysical characteristics and places the risk of performance on the buyer is a: · a. Design specification b. Functional specification c. Performance specification d. Project specification e. All of the above