Scrum True or Fals If a non-critical, cosmetic, but complex bug is discovered to

ID: 3752849 • Letter: S

Question

Scrum True or Fals

If a non-critical, cosmetic, but complex bug is discovered towards the end of a Sprint the team should focus all their energy and effort to fix it at the detriment of the other features (i.e., the bug is implicitly given top priority in order to be fixed by the end of the sprint).

The use of story points and relative estimation for stories is purely done because of historical reasons, but story points could be replaced with effort hours since humans are outstanding at estimating the absolute duration of tasks

During the Poker Planning activity for estimating a particular story, if four developers reveal 4, 7, 13 and 2 then developers with estimates of 2 and 13 will have to discuss their choice with the team.

The purpose of a Backlog Grooming meeting performed during the middle of Sprint N, is to re-prioritize the work needed to be done in the second part of Sprint N.

During the Poker Planning activity for estimating a particular story, if eight developers reveal 4, 5, 7, 6, 5, 4, 6 and 6 on their cards, the Scrum Master will use the average of these values to estimate the story, since the values of the teams are very close to each other.

If a team encounters problems delivering features to the client after one or two sprints, or if the team cannot find their “rhythm” after one or two sprints the team should switch to a Waterfall process, because things are not going to improve if the team continues with Scrum.

Explanation / Answer

Answer : If a non-critical, cosmetic, but complex bug is discovered towards the end of a Sprint the team should focus all their energy and effort to fix it at the detriment of the other features (i.e., the bug is implicitly given top priority in order to be fixed by the end of the sprint).

False , as bug is non critical , one person can work on this

The use of story points and relative estimation for stories is purely done because of historical reasons, but story points could be replaced with effort hours since humans are outstanding at estimating the absolute duration of tasks

False

During the Poker Planning activity for estimating a particular story, if four developers reveal 4, 7, 13 and 2 then developers with estimates of 2 and 13 will have to discuss their choice with the team.

True as we did not get enough majority

The purpose of a Backlog Grooming meeting performed during the middle of Sprint N, is to re-prioritize the work needed to be done in the second part of Sprint N.

False , Backlog Grooming is to discuss stories of next spring

During the Poker Planning activity for estimating a particular story, if eight developers reveal 4, 5, 7, 6, 5, 4, 6 and 6 on their cards, the Scrum Master will use the average of these values to estimate the story, since the values of the teams are very close to each other.

False, he will take mojority

If a team encounters problems delivering features to the client after one or two sprints, or if the team cannot find their “rhythm” after one or two sprints the team should switch to a Waterfall process, because things are not going to improve if the team continues with Scrum.

False, we should not switch