A project plan developed in MS Project has over committed resources. Resource le
ID: 377204 • Letter: A
Question
A project plan developed in MS Project has over committed resources. Resource leveling may or may not increase the duration of the project, but can not decrease the duration of the project.
True
False
In order to successfully implement a PMO a firm must first develop a detailed project management methodology.
True
False
It is important to develop a change control process before the project starts.
True
False
Since most projects don't have changes to scope, it is not necessary to develop a change control process before the first change is identified.
True
False
Explanation / Answer
1. Answer is True. Resource leveling is mainly used to balance the demand of resources with the supply.
2. Answer is False. PMO is not only about methodology. It is about many things like strategy, culture, high performance, etc.
3. Answer is True. Change control process helps the teams in altering scope of work, with set policies and processes.
4. Answer is False. No scope can be perfect, hence change control has to be there.