Complete the following MRP record. Initial inventory is zero for all parts. Safe

ID: 378775 • Letter: C

Question

Complete the following MRP record. Initial inventory is zero for all parts. Safety stock is zero, and lead time is 1 period for all parts.

Copy the MRP charts, and paste in the answer area. Complete the MRP records

Bill of materials


Period

1

2

3

4

5

Part M

Gross Requirement

100

200

Lot size=200, Lead time=1, safety stock=0

Scheduled Receipts

Projected Available Balance

Planned Order Release

Period

1

2

3

4

5

Part P

Gross Requirement

Lot for Lot, Lead time=1, safety stock=0

Scheduled Receipts

Projected Available Balance

Planned Order Release

Period

1

2

3

4

5

Part Q

Gross Requirement

Lot for Lot, Lead time=1, safety stock=0

Scheduled Receipts

Projected Available Balance

Planned Order Release

Period

1

2

3

4

5

Part M

Gross Requirement

100

200

Lot size=200, Lead time=1, safety stock=0

Scheduled Receipts

Projected Available Balance

Planned Order Release

Period

1

2

3

4

5

Part P

Gross Requirement

Lot for Lot, Lead time=1, safety stock=0

Scheduled Receipts

Projected Available Balance

Planned Order Release

Period

1

2

3

4

5

Part Q

Gross Requirement

Lot for Lot, Lead time=1, safety stock=0

Scheduled Receipts

Projected Available Balance

Planned Order Release

TP Q (4 required) Q (2 required)

Explanation / Answer

Period

1

2

3

4

5

Part M

Gross Requirement

100

200

Lot size=200, Lead time=1, safety stock=0

Scheduled Receipts

0

0

0

0

0

Projected Available Balance

0

0

0

100

0

Planned Order Release

200

100

Period

1

2

3

4

5

Part P

Gross Requirement

0

0

200

100

0

Lot for Lot, Lead time=1, safety stock=0

Scheduled Receipts

0

0

0

0

0

(GR=planned order release of M *1)

Projected Available Balance

0

0

0

0

0

Planned Order Release

200

100

Period

1

2

3

4

5

Part Q

Gross Requirement

0

400

1000

400

0

Lot for Lot, Lead time=1, safety stock=0

Scheduled Receipts

0

0

0

0

0

(GR=planned order release of P *2+planned order release of M *4)

Projected Available Balance

0

0

0

0

0

Planned Order Release

400

1000

400

0

0

Period

1

2

3

4

5

Part M

Gross Requirement

100

200

Lot size=200, Lead time=1, safety stock=0

Scheduled Receipts

0

0

0

0

0

Projected Available Balance

0

0

0

100

0

Planned Order Release

200

100

Period

1

2

3

4

5

Part P

Gross Requirement

0

0

200

100

0

Lot for Lot, Lead time=1, safety stock=0

Scheduled Receipts

0

0

0

0

0

(GR=planned order release of M *1)

Projected Available Balance

0

0

0

0

0

Planned Order Release

200

100

Period

1

2

3

4

5

Part Q

Gross Requirement

0

400

1000

400

0

Lot for Lot, Lead time=1, safety stock=0

Scheduled Receipts

0

0

0

0

0

(GR=planned order release of P *2+planned order release of M *4)

Projected Available Balance

0

0

0

0

0

Planned Order Release

400

1000

400

0

0