Complete the following MRP record. Initial inventory is zero for all parts. Safe
ID: 378775 • Letter: C
Question
Complete the following MRP record. Initial inventory is zero for all parts. Safety stock is zero, and lead time is 1 period for all parts.
Copy the MRP charts, and paste in the answer area. Complete the MRP records
Bill of materials
Period
1
2
3
4
5
Part M
Gross Requirement
100
200
Lot size=200, Lead time=1, safety stock=0
Scheduled Receipts
Projected Available Balance
Planned Order Release
Period
1
2
3
4
5
Part P
Gross Requirement
Lot for Lot, Lead time=1, safety stock=0
Scheduled Receipts
Projected Available Balance
Planned Order Release
Period
1
2
3
4
5
Part Q
Gross Requirement
Lot for Lot, Lead time=1, safety stock=0
Scheduled Receipts
Projected Available Balance
Planned Order Release
Period
1
2
3
4
5
Part M
Gross Requirement
100
200
Lot size=200, Lead time=1, safety stock=0
Scheduled Receipts
Projected Available Balance
Planned Order Release
Period
1
2
3
4
5
Part P
Gross Requirement
Lot for Lot, Lead time=1, safety stock=0
Scheduled Receipts
Projected Available Balance
Planned Order Release
Period
1
2
3
4
5
Part Q
Gross Requirement
Lot for Lot, Lead time=1, safety stock=0
Scheduled Receipts
Projected Available Balance
Planned Order Release
TP Q (4 required) Q (2 required)Explanation / Answer
Period
1
2
3
4
5
Part M
Gross Requirement
100
200
Lot size=200, Lead time=1, safety stock=0
Scheduled Receipts
0
0
0
0
0
Projected Available Balance
0
0
0
100
0
Planned Order Release
200
100
Period
1
2
3
4
5
Part P
Gross Requirement
0
0
200
100
0
Lot for Lot, Lead time=1, safety stock=0
Scheduled Receipts
0
0
0
0
0
(GR=planned order release of M *1)
Projected Available Balance
0
0
0
0
0
Planned Order Release
200
100
Period
1
2
3
4
5
Part Q
Gross Requirement
0
400
1000
400
0
Lot for Lot, Lead time=1, safety stock=0
Scheduled Receipts
0
0
0
0
0
(GR=planned order release of P *2+planned order release of M *4)
Projected Available Balance
0
0
0
0
0
Planned Order Release
400
1000
400
0
0
Period
1
2
3
4
5
Part M
Gross Requirement
100
200
Lot size=200, Lead time=1, safety stock=0
Scheduled Receipts
0
0
0
0
0
Projected Available Balance
0
0
0
100
0
Planned Order Release
200
100
Period
1
2
3
4
5
Part P
Gross Requirement
0
0
200
100
0
Lot for Lot, Lead time=1, safety stock=0
Scheduled Receipts
0
0
0
0
0
(GR=planned order release of M *1)
Projected Available Balance
0
0
0
0
0
Planned Order Release
200
100
Period
1
2
3
4
5
Part Q
Gross Requirement
0
400
1000
400
0
Lot for Lot, Lead time=1, safety stock=0
Scheduled Receipts
0
0
0
0
0
(GR=planned order release of P *2+planned order release of M *4)
Projected Available Balance
0
0
0
0
0
Planned Order Release
400
1000
400
0
0