Consider the following information on job times and due dates (in hours). Job Jo
ID: 380524 • Letter: C
Question
Consider the following information on job times and due dates (in hours).
Job
Job Time
Due Date
A
3.50
6.00
B
2.50
5.00
C
5.50
16.00
D
4.25
18.00
E
2.75
3.00
You are asked to determine the processing sequence using Shortest Processing Time (SPT) and Earliest Due Date (EDD) rule; and to decide which sequence is better for average job flow time and the average job tardiness performance measures.
FORMAT FOR ENTRIES:
• Sequence should be entered in the following format: D-E-B-C-A (with no spaces)
• Values for performance measures will be entered with two decimals after dot (5.00)
Enter the sequence using SPT rule: _________
For SPT sequence, provide the following performance measure values: __________
Average job flow time:________ and __________
Average job tardiness: ._____________
Enter the sequence using EDD rule: ___________
For EDD sequence, provide the following performance measure values:___________
Average job flow time:___________ and
Average job tardiness: .____________
Based on average job flow time, which sequence is better? (Enter SPT, EDD, EITHER):
Based on average job tardiness, which sequence is better? (Enter SPT, EDD, EITHER):
Please Show how problem was solve Thank you ?
Job
Job Time
Due Date
A
3.50
6.00
B
2.50
5.00
C
5.50
16.00
D
4.25
18.00
E
2.75
3.00
Explanation / Answer
1) SPT is the shortest processing time: the Shortest job has to be taken first. Sequence using SPT rule: B-E-A-D-C
2) Average job flow time: (3.5+2.5+5.5+4.25+2.75)/5 = 18.5/5 = 3.7
3) Average Job Tardiness: If the job time is less than due date then we consider it as zero. If the job time is more than due date then the difference of both has to be taken.
Average Job Tardiness = (0+0+0+0+0)/5 = 0
4) Earliest Due Date: EDD rule: Jobs are sequenced based on their earliest due date. It means the one which goes out of the system first.
Sequence using EDD rule - E-B-A-C-D
Average job flow time = (6+5+16+18+3)/5 = 48/5 = 9.6
Average job tardiness = 0
Based on average job flow time, SPT is better (Since SPT = 3.7 and EDD= 9.6, shortest time has to be taken )
Based on average job tardiness, Either of them is better (Both are zero)