projects on a scale from 1 to 10, you create the matrix shown in the exhibit. (C
ID: 3809460 • Letter: P
Question
projects on a scale from 1 to 10, you create the matrix shown in the exhibit. (Click the Exhibit(s) button.) Which project should you recommend? Project W Project X Project Y Project Z You are given the network diagram with durations in weeks shown in the exhibit Which statement is true about this Project? The slack for task G is 13. The ES for task c is week 8 The LS for tasks H is week 18 The project has multiple critical paths You are given the network diagram with durations in weeks shown in the exhibit.Explanation / Answer
Question:2
If we see the network diagram and do some analysis then we found that:
4) The project has multiple critical paths
Reason: There are various reasons for chosing this 4th option:
1) There are following multiple paths like:
a) Start->A->B->C->D->Finish
b) Start->E->F->Finish
c) Start->G->H->Finish
So for task complition we need to simultaniously work on these three multiple paths.