on this question I missed on the (AFG) path for the mean and standard deviation.
ID: 382475 • Letter: O
Question
on this question I missed on the (AFG) path for the mean and standard deviation. can you show me the correct solution?
Problem 17-12
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.
Use Table B1 and Table B2.
Activity Immediate
Predecessor Estimated Times (weeks)
A — 2-4-6
D A 6-8-10
E D 7-9-12
H E 2-3-5
F A 3-4-8
G F 5-7-9
B — 2-2-3
I B 2-3-6
J I 3-4-5
K J 4-5-8
C — 5-8-12
M C 1-1-1
N M 6-7-11
O N 8-9-13
End H, G, K, O
If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus. (Round path means and path standard deviations to 2 decimal places. Round probabilities to 4 decimal places. Do not round any other intermediate calculations.)
Explanation / Answer
c-m-n-o is the critical path.
Probability ($1000) = Prob (Completion <= 26) = NORM.DIST(26,26.17,1.66,TRUE) = 0.4592
Probability ($1000) = Prob (Completion <= 27) = NORM.DIST(27,26.17,1.66,TRUE) = 0.6915
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.