Test: Exam 4 Time Remaining: 01:56:09 Submit Test This Question: 1 pt 110137 (6 complete) This Test: 37 pts possible Using Johnson's rule for 2-machine scheduling, the sequence is Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting Processing times are as Scheduled Order Job Operation 1 hours) Operation 2 hours) Job 10 14 12 Forthe schedle developed usrg Johnson's rueth-totai length of time taken to complete the six-ma inth2nd operation).hours (enter your response as a whole number) Enter your answer in the answer box HOP NO

Explanation / Answer

Time taken to complete the jobs = 34 hours

Job Assigned to operation Time taken A Operation 1 4 B Operation 2 5 C Operation 1 3 D Operation 2 14 E Operation 2 1 F Operation 1 7
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote