19. There was recently a natural disaster that hit your company’s data center that physically destroyed all IT systems in the data center. Per your company’s, BCP/DR it is expected that all critical systems should be back online within 4 hours. This objective best describes which of the following: a. The company’s Recovery Point Objective (RPO)
b. The company’s Recovery Time Objective (RTO)
c. The company’s offsite storage requirements
d. The company’s Business Continuity Objective (BCO)
20. Having the humidity set at certain specification to avoid to much moisture in the air within your data center is an example of: a. Data center controls
b. Environmental controls
c. Physical security controls
d. Back-up and recovery controls
Explanation / Answer
Answer for 19.
As per BCP i.e. Business Continuity Planning, after the disaster occured , option 'd' is perfectly suitable for the scenario and option 'b' is suitable for DR i.e. Disaster Recovery. But we have a given time to recover all the system so the most suitable objective is option 'b' i.e. The company's Recovery Time Objective(RTO).
Answer for 20.
b.Environmental control.
because its straight forward about the environment of data center.