2. The following table indicates the activity, and time duration of each task in

ID: 3851566 • Letter: 2

Question

2. The following table indicates the activity, and time duration of each task in the development of a project:

Activity

Description

Duration (Days)

Immediate Predecessor

A

Requirement Analysis

5

-

B

System Design

15

A

C

Implementation

25

B

D

Telecommunication

15

B

E

Equipment Installation

30

B

F

System Integration

10

C, D

G

System Testing

10

E, F

H

Training

5

G

I

System Deployment

5

H

a) Draw the network for the information provided in the table (12 pts.)

b) Determine (specify) all paths through the network (9 pts.)

c) Determine the Critical Path(s) (7 pts.)

d) Calculate the planned duration of the project (8 pts.)

e) Determine the ES, EF, LS, and LF for Activity A and Activity B, (24 pts.)

Activity 1:                                      Activity 2:

ES =______________________                 ES =____________________________

EF = _______________________               EF = ____________________________

LS = _______________________               LS = ____________________________

LF = _______________________              LF = ____________________________

Activity

Description

Duration (Days)

Immediate Predecessor

A

Requirement Analysis

5

-

B

System Design

15

A

C

Implementation

25

B

D

Telecommunication

15

B

E

Equipment Installation

30

B

F

System Integration

10

C, D

G

System Testing

10

E, F

H

Training

5

G

I

System Deployment

5

H

Explanation / Answer

Activity

Description

Duration (Days)

Immediate Predecessor

Critical Path

Network Duration

A

Requirement Analysis

5

-

25

1000ms

B

System Design

15

A

51

5600ms

C

Implementation

25

B

24

2305ms

D

Telecommunication

15

B

10

4501ms

E

Equipment Installation

30

B

22

9512ms

F

System Integration

10

C, D

95

2548ms

G

System Testing

10

E, F

34

6514ms

H

Training

5

G

15

5214ms

I

System Deployment

5

H

25

3521ms

Activity1

ES=2548ms

EF=6502ms

LS=6582ms

LF=0215ms

Activity2:

ES=5425ms

EF=2065ms

LS=8524ms

LF=2649ms

Activity

Description

Duration (Days)

Immediate Predecessor

Critical Path

Network Duration

A

Requirement Analysis

5

-

25

1000ms

B

System Design

15

A

51

5600ms

C

Implementation

25

B

24

2305ms

D

Telecommunication

15

B

10

4501ms

E

Equipment Installation

30

B

22

9512ms

F

System Integration

10

C, D

95

2548ms

G

System Testing

10

E, F

34

6514ms

H

Training

5

G

15

5214ms

I

System Deployment

5

H

25

3521ms