You are the project manager for Changing Tides video games. You have gathered th
ID: 3853677 • Letter: Y
Question
You are the project manager for Changing Tides video games. You have gathered the inputs for the Estimate Activity Durations process. Which of the following tools and techniques will you employ to produce the outputs for this process?
Activity list, expert judgment, alternatives analysis, analogous estimating, parametric estimating, three-point estimating, and reserve analysis
Activity list, expert judgment, analogous estimating, parametric estimating, group decision-making techniques, and three-point estimating
Expert judgment, analogous estimating, parametric estimating, three-point estimating, group decision-making techniques, and reserve analysis
Expert judgment, alternatives analysis, analogous estimating, parametric estimating, three-point estimating, and group decision-making techniques
Explanation / Answer
Answer: option C
Expert judgment, analogous estimating, parametric estimating, three-point estimating, group decision-making techniques, and reserve analysis
Explanation:
as a project manager first we take suggestions from the the Expert.Always respect the Expert judgment after that we have the estimate the cost ,parametric estimating, three-point estimating of the project with all other experts as group decision-making techniques, and after finally take a reserve analysis