What is the first thing that should happen when a new change request comes in? I

ID: 3857500 • Letter: W

Question

What is the first thing that should happen when a new change request comes in?

It should be evaluated for feasibility

It should be assigned a tracking number

A determination is made as to whether the person or entity submitting the change request is a valid stakeholder in the project

The project sponsor is notified

A.

It should be evaluated for feasibility

B.

It should be assigned a tracking number

C.

A determination is made as to whether the person or entity submitting the change request is a valid stakeholder in the project

D.

The project sponsor is notified

Explanation / Answer

First we need to authorize the request, that it is coming from an authentic person who has the right to request for change. Then its feasibility can be checked and project sponsor should be notified. Then we can assign it a tracking number.

So (C) should be the first thing to do.