Everbuilt Company had no jobs in progress at the beginning of June and no beginning inventories. It started only two jobs during June—Job L and Job W. Job L was completed and sold by the end of June and Job W was incomplete at the end of June. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs L and W (all data and questions relate to the month of June):

Estimated total fixed manufacturing overhead. . . . . . . . . . . . . . . . . . . . . . . . . .        $30,000

Estimated variable manufacturing overhead per

direct labor-hour. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $3.00

Estimated total direct labor hours to be worked. . . . . . . . . . . . . . . . . . . . . . . . .        6,000

Total actual manufacturing overhead costs incurred. . . . . . . . . . . . . . . . . . . . .         $37,500

Job L             Job W

Direct materials. . . . . . . . . . . . . . . . . . . . . . $39,000           $24,000

Direct labor cost. . . . . . . . . . . . . . . . . . . . . . $62,000           $22,500

Actual direct labor hours worked. . . . . . . .    4,200             1,500

What is the company’s predetermined overhead rate?

Please give step by step instructions

Explanation / Answer

Predetermined overhead rate = Estimated total manufacturing overhead cost / Estimated direct labor hours

= (30000 + 3*6000) / 6000 = $ 8 per direct labor hour

Variable portion of Predetermined overhead rate = $3

Fixed portionPredetermined overhead rate = $5