The following activities are part of a project to be scheduled using CPM: ACTIVI
ID: 387209 • Letter: T
Question
The following activities are part of a project to be scheduled using CPM:ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 6 B A 6 C A 7 D C 2 E B, D 4 F D 3 G E, F 7
How much slack does activity B have? Slack of activity B The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 6 B A 6 C A 7 D C 2 E B, D 4 F D 3 G E, F 7
How much slack does activity B have?
Explanation / Answer
Slack of activity B=6 weeks , 15-9
If you think this helped do give a thumbs up else share your queries in comment section .
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.