Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

4. Provided the following table, how many weeks long is the critical path? Durat

ID: 387613 • Letter: 4

Question

4. Provided the following table, how many weeks long is the critical path? Duration (in weeks) Preceding Activity Start Start Start A, E F, B D, G 0 Finish 5. Given the table above, describe the effect of Activity D taking twice as long as planned. 6. An activity has 3 estimates, provided below: a. Optimistic 10 days. b. Pessimistic 25 days c. Realistic 15 days d. QUESTION: What is the three-point estimate for this activity? 7. What is the standard deviation for the activity in the above question? 8. Given the project network node depicted below, fill n the value in the missing quadrant, and calculate the duration and the float for the activity. 23 21 Duration? FHoat ? 37 39

Explanation / Answer

It is 15 weeks long

Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Start A X X X X X X E X B X X F X C X X D X X X G X X X X X X X End
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote