QUESTION 16 A risk assessment is created that records the work to be done, who w

ID: 3877410 • Letter: Q

Question

QUESTION 16

A risk assessment is created that records the work to be done, who will do it, the development schedule and the work products.

True

False

1 points   

QUESTION 17

Bar charts are the most commonly used representation for project schedules. They show the schedule as activities or resources against time.

True

False

1 points   

QUESTION 18

Algorithmic cost modeling is the estimate of future effort requirements is based on the manager’s experience of past projects and the application domain. Essentially, the manager makes an informed judgment of what the effort requirements are likely to be.

True

False

1 points   

QUESTION 19

Experience-based techniques rely on judgments based on experience of past projects and the effort expended in these projects on software development activities.

True

False

1 points   

QUESTION 20

Risk management techniques for software may be experience-based, where managers judge the effort required, or algorithmic, where the effort required is computed from other estimated project parameters.

True

False

Explanation / Answer

QUESTION 16 - False

Explanation:- A risk assesments not created the record.it is a simple approach to do the project work further with some risk.it never do development schedule and the work products.

QUESTION 17- True

Explanation:- Bar charts are the most commonly used representation for project schedules. They show the schedule as activities or resources against time.it also show the progress of the project.it is the easiest way to determine the project status.

QUESTION 18- False

QUESTION 19- True

QUESTION 20- True