Cherokee Histo x Sign out x × Students-MyEX Assignments: 2 xy L CH 3 Capacity i × How to take a s × Dashboard × e chegg Study I x" e B. Find The Mu × C Not Secure ezto.mheducation.com/hm.tpx Chaln Management: Online Fall 2018 CH 3 Capacity Planning instru Question 2 (of ) Save & Exit 10.00 points Problem 3-2 Given the folowing information. Maxmum capacity (labor hours) ElTeclive capacity ratio. Actual time worked 490 hcurs per week 82% 307 hcurs per week over the last two weeks 67 percent of the jobs are being completed on time On-time delivery %; a. Calculate the cffective capacity and actual utilization. (Round your answers to 2 decimal places) Effective capacity Actual utilization b. Do we need to add more capacity? No Difficulty: 2 Medium Problem 3-2 Leaming Objective: 03-05 Explain the impacts of bottlenecks, variance, and other factors on procass Check my workExplanation / Answer
a. effective capacity ratio is 82% and maximum capacity available is 490 hours per week.
the effective capacity= 490*82%= 401.8 hours
actual utilization is= 307/401.8= 76.406%
b. Yes, we need to improve the capacity or add more capacity
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.